Official Surveys prove feasibility of Elbe Tunnel
An Elbe tunnel at the same location as the planned bridge with
the same traffic performance and link roads to the existing road
network is technically feasible. The alleged problems (ventilation
and security matters) are technically solvable. The building
ground enables a tunnel construction and the costs of the tunnel
solution are comparable with the bridge model.
Already since the beginning of the nineties an Elbe tunnel was
considered by Dresden Municipal Council to be an alternative
to the bridge model. Several engineering consultants suggested
their plans and referred to the technical feasibility. But the
municipal administration this proposals always negated.
In autumn 2003, the regulatory authorities in the approval procedure
for the bridge model, called on to the mayor again to investigate
the tunnel possibility adequately. Thereupon, the planning office
EIBS compiled
another survey, which again ascertained the technical
feasibility of an Elbe tunnel. This position in April 2004 was
confirmed by additional investigations of the planning offices ILF,
Innsbruck-Munich-Berlin and BAUGRUND,
Dresden.
An additional planning and approval period of 12-16 months would
be sufficient to implement an Elbe tunnel.
|